Teatro delle Passioni comes back to life

In the heart of Modena’s former ENEL power station, Cavea Engineering developed the design for the stage engineering and multimedia systems of the Teatro delle Passioni. The works began in 2023 and were presented on 16th June, celebrating the return to the city of a modern theatre created within a landmark of industrial heritage

The City of Modena’s redevelopment plan for the former ENEL power station included, among other works, converting one of its areas into a modern production theatre able to host the activities of the existing Teatro delle Passioni, part of the programme of Emilia-Romagna Teatro ERT / Teatro Nazionale. For the new venue we designed a complete, integrated stage engineering system: an infrastructure serving the multimedia and stage systems, a control and power system for stage lighting, and a set of motorised trusses and hoists for both the auditorium and the stage.
The result is a system able to meet the production needs of a contemporary theatre while working within the constraints of an existing building, converted from a power station into a performance space.

The context

The Teatro delle Passioni stands in the former AMCM / ENEL power station complex, within Modena’s Parco della Creatività. The project, the second phase of the area’s regeneration promoted by the City of Modena and funded by the PNRR (Italy’s National Recovery and Resilience Plan), gives the city back a historic building tied to its industrial memory, transforming it into a multifunctional cultural space.

Architect Roberta Fusari, of the City of Modena’s Special Projects Management Department, described her experience: “The project, funded by PNRR resources for urban regeneration, made it possible to complete the new theatre: the 210-seat auditorium, with its large stage machinery, the technical services tower with its support spaces and the guest quarters for visiting companies complement the spaces already in use since 2023, and enrich the former AMCM area, now fully restored, with an important cultural hub that is much loved by the public.

We have reached the end of the works and handed over a theatre fully equipped with everything it needs. It was very interesting to work simultaneously on the restoration of the building and on its technical fit-out, alongside specialised technicians, including Cavea Engineering, and in constant dialogue with ERT’s needs. Personally, I discovered an almost artisanal expertise within a highly technical and extremely creative context.”

The project and results

Infrastructure
We designed the infrastructure for stage lighting, from the preparation of the house and stage trusses to the circuits for powering and controlling the lighting fixtures. A total of 72 dimmer circuits were provided, together with Sensor CEM3 processors, triple-mode ThruPower power modules, and DMX512-A/sACN/RDM gateways/splitters that are interoperable across different manufacturers.

Stage machinery control panels
A main control panel with a pendant push-button station operates the hoists and motorized trusses, alongside a secondary panel for power distribution.

Motorized house and stage trusses
The house trusses are now self-lifting and fitted with hybrid power/data/DMX cabling; the stage trusses are equipped with motorized chain hoists and safety pretensioners for the suspended load.

PLB (Production Lighting Box)
Power and multimedia signals are distributed across the house, the stage and the control room through PLBs: configurable access points for signals and power, designed to adapt quickly to the needs of modern productions.

Networking
We chose to manage multimedia signals through a managed Layer 3 switch, with routing capabilities and PoE+ to power cameras or small devices without running dedicated power cables. It is dedicated to AV-over-IP signals, with specific features for the protocols most commonly used in live entertainment (Dante and AES67 for audio, NDI and NVX for video, etc.).

Fly gallery and tormentors
A steel structure verified according to NTC2018* (Italian Technical Standards for Construction 2018) provides high-level access to the stage equipment, with three movable tormentor systems.

The outcome of this project is a flexible, reconfigurable stage engineering infrastructure, designed to support both ERT’s season productions and the needs of visiting companies. Today’s productions increasingly integrate multimedia elements, such as video capture and projection, multichannel audio and dynamic lighting, as an integral part of their artistic language.

“Although today we design multimedia environments in a wide range of settings, from offices to training rooms, theatre remains one of our specialisms. It is also among the projects we love most, because theatre is where we started,” said Luca Dallaturca, CEO and co-founder of Cavea Engineering. “For the Teatro delle Passioni we created an infrastructure that integrates stage engineering with the management of electrical power and multimedia signals: the theatre is now ready to host performances in step with the most modern experimentation. We would like to thank all the professionals we worked with, in particular Politecnica Ingegneria e Architettura, architect Roberta Fusari, the project’s RUP (Sole Project Manager), and of course the City of Modena, which chose to relocate the Teatro delle Passioni to a building suited to its vocation.”